How long does a Residential Improvement Project permit take in Whitehorn, Calgary?
Median days · Applied → Issued
36 days
Sample: 98 permits, last 24 months
Median days · Issued → Completed
106 days
From permit issuance to completion
City-wide median
17 days
Whitehorn is 19 days slower
Recent examples in Whitehorn
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06946 | Improvement | — | 2026-04-27 | 2026-09-11 | 137 | $10K |
| BP2026-07395 | Improvement | — | 2026-05-01 | 2026-09-10 | 132 | $44K |
| BP2026-13396 | New | — | 2026-07-17 | 2026-09-09 | 54 | $72K |
| BP2026-15175 | Improvement | — | 2026-08-11 | 2026-09-06 | 26 | $9K |
| BP2026-14588 | New | — | 2026-08-04 | 2026-08-26 | 22 | $10K |