How long does a Commercial / Multi Family Project permit take in Whitehorn, Calgary?
Median days · Applied → Issued
76 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
89 days
From permit issuance to completion
City-wide median
42 days
Whitehorn is 34 days slower
Recent examples in Whitehorn
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05997 | Improvement | — | 2026-04-15 | 2026-07-15 | 91 | $17M |
| BP2025-17684 | Improvement | — | 2025-09-10 | 2026-03-17 | 188 | $20K |
| BP2026-00133 | Improvement | — | 2026-01-05 | 2026-02-13 | 39 | $0 |
| BP2025-15264 | Improvement | — | 2025-08-06 | 2025-09-25 | 50 | $0 |
| BP2025-04375 | Improvement | — | 2025-03-14 | 2025-05-29 | 76 | $200K |