How long does a Residential Improvement Project permit take in University Heights, Calgary?
Median days · Applied → Issued
20 days
Sample: 30 permits, last 24 months
Median days · Issued → Completed
141 days
From permit issuance to completion
City-wide median
17 days
University Heights is 3 days slower
Recent examples in University Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13716 | Improvement | Jouge Homes | 2026-07-22 | 2026-07-31 | 9 | $8K |
| BP2026-05746 | New | Riverside Developments | 2026-04-12 | 2026-04-28 | 16 | $78K |
| BP2026-02677 | Improvement | Grit Renovation Projects | 2026-02-23 | 2026-04-08 | 44 | $421K |
| BP2026-02893 | Improvement | Riverside Developments | 2026-02-25 | 2026-03-29 | 32 | $6K |
| BP2026-00110 | Improvement | Feegrade Contracting | 2026-01-05 | 2026-02-10 | 36 | $500K |