How long does a Commercial / Multi Family Project permit take in University Heights, Calgary?
Median days · Applied → Issued
38 days
Sample: 44 permits, last 24 months
Median days · Issued → Completed
179 days
From permit issuance to completion
City-wide median
42 days
University Heights is 4 days faster
Recent examples in University Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08795 | Unspecified | — | 2026-05-20 | 2026-07-21 | 62 | $15K |
| BP2026-08797 | Unspecified | — | 2026-05-20 | 2026-07-21 | 62 | $34K |
| BP2026-08839 | Unspecified | — | 2026-05-20 | 2026-07-21 | 62 | $40K |
| BP2026-10502 | Unspecified | — | 2026-06-09 | 2026-06-22 | 13 | $7K |
| BP2026-07838 | Improvement | — | 2026-05-07 | 2026-06-02 | 26 | $1.6M |