How long does a Commercial / Multi Family Project permit take in University Heights, Calgary?

Rolling 24 months · Sample: 44
Median days · Applied → Issued
38 days
Sample: 44 permits, last 24 months
Median days · Issued → Completed
179 days
From permit issuance to completion
City-wide median
42 days
University Heights is 4 days faster

Recent examples in University Heights

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08795Unspecified2026-05-202026-07-2162$15K
BP2026-08797Unspecified2026-05-202026-07-2162$34K
BP2026-08839Unspecified2026-05-202026-07-2162$40K
BP2026-10502Unspecified2026-06-092026-06-2213$7K
BP2026-07838Improvement2026-05-072026-06-0226$1.6M