How long does a Single Construction Permit permit take in Undefined, Calgary?
Median days · Applied → Issued
24 days
Sample: 8 permits, last 24 months
City-wide median
18 days
Undefined is 6 days slower
Recent examples in Undefined
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11053 | New | Cedarglen Group | 2026-06-16 | 2026-07-10 | 24 | $340K |
| BP2026-10152 | New | Cedarglen Group | 2026-06-04 | 2026-07-03 | 29 | $277K |
| BP2026-07842 | New | Excel Homes | 2026-05-07 | 2026-06-11 | 35 | $325K |
| BP2026-08457 | New | Shane Homes | 2026-05-14 | 2026-06-07 | 24 | $268K |
| BP2026-06563 | New | Cedarglen Group | 2026-04-22 | 2026-05-22 | 30 | $398K |