How long does a Commercial / Multi Family Project permit take in Undefined, Calgary?
Median days · Applied → Issued
180 days
Sample: 14 permits, last 24 months
Median days · Issued → Completed
370 days
From permit issuance to completion
City-wide median
42 days
Undefined is 138 days slower
Recent examples in Undefined
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-03539 | New | Mattamy Homes | 2026-03-09 | 2026-04-07 | 29 | $814K |
| BP2025-03926 | New | Partners Development Group | 2025-03-07 | 2025-12-04 | 272 | $12.8M |
| BP2025-05789 | New | Partners Development Group | 2025-04-03 | 2025-04-15 | 12 | $1.3M |
| BP2024-22342 | New | City Vibe Developments | 2024-10-21 | 2025-03-17 | 147 | $57K |
| BP2024-21925 | New | Partners Development Group | 2024-10-15 | 2024-10-28 | 13 | $1.5M |