How long does a Residential Improvement Project permit take in Tuscany, Calgary?
Median days · Applied → Issued
12 days
Sample: 211 permits, last 24 months
Median days · Issued → Completed
54 days
From permit issuance to completion
City-wide median
17 days
Tuscany is 5 days faster
Recent examples in Tuscany
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14721 | New | Gecko Projects | 2026-08-05 | 2026-08-25 | 20 | $56K |
| BP2026-14027 | Improvement | Maverick Decks Bnb Barrels | 2026-07-26 | 2026-08-17 | 22 | $10K |
| BP2026-12406 | Improvement | Denning Enterprise | 2026-07-03 | 2026-08-13 | 41 | $55K |
| BP2026-13840 | Improvement | — | 2026-07-23 | 2026-08-12 | 20 | $12K |
| BP2026-13909 | Improvement | Canadas Best Decks and Railings | 2026-07-24 | 2026-08-12 | 19 | $4K |