How long does a Commercial / Multi Family Project permit take in Tuscany, Calgary?
Median days · Applied → Issued
15 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
127 days
From permit issuance to completion
City-wide median
42 days
Tuscany is 27 days faster
Recent examples in Tuscany
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06431 | Unspecified | — | 2026-04-21 | 2026-04-29 | 8 | $85K |
| BP2025-23828 | Improvement | — | 2025-12-17 | 2026-03-31 | 104 | $8K |
| BP2025-22646 | Unspecified | — | 2025-11-25 | 2025-12-09 | 14 | $10K |
| BP2025-20591 | Improvement | — | 2025-10-21 | 2025-11-17 | 27 | $22K |
| BP2025-20595 | Improvement | — | 2025-10-21 | 2025-11-07 | 17 | $17K |