How long does a Single Construction Permit permit take in Thorncliffe, Calgary?

Rolling 24 months · Sample: 12
Median days · Applied → Issued
48 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
330 days
From permit issuance to completion
City-wide median
18 days
Thorncliffe is 30 days slower

Recent examples in Thorncliffe

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-09647NewInfill Homes2026-05-292026-08-2588$696K
BP2026-03401NewPiltover2026-03-052026-04-2248$242K
BP2026-03403NewPiltover2026-03-052026-04-2248$242K
BP2025-22995NewMann Builders2025-12-012026-01-1646$285K
BP2025-23660NewSaville Homes2025-12-132026-01-0927$470K