How long does a Single Construction Permit permit take in Thorncliffe, Calgary?
Median days · Applied → Issued
48 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
330 days
From permit issuance to completion
City-wide median
18 days
Thorncliffe is 30 days slower
Recent examples in Thorncliffe
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-09647 | New | Infill Homes | 2026-05-29 | 2026-08-25 | 88 | $696K |
| BP2026-03401 | New | Piltover | 2026-03-05 | 2026-04-22 | 48 | $242K |
| BP2026-03403 | New | Piltover | 2026-03-05 | 2026-04-22 | 48 | $242K |
| BP2025-22995 | New | Mann Builders | 2025-12-01 | 2026-01-16 | 46 | $285K |
| BP2025-23660 | New | Saville Homes | 2025-12-13 | 2026-01-09 | 27 | $470K |