How long does a Commercial / Multi Family Project permit take in Thorncliffe, Calgary?
Median days · Applied → Issued
43 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
166 days
From permit issuance to completion
City-wide median
42 days
Thorncliffe is 1 days slower
Recent examples in Thorncliffe
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11621 | Improvement | — | 2026-06-24 | 2026-08-05 | 42 | $5K |
| BP2026-11001 | Improvement | — | 2026-06-16 | 2026-07-23 | 37 | $75K |
| BP2025-19222 | New | Kz Contracting | 2025-09-30 | 2026-06-17 | 260 | $678K |
| BP2025-23792 | Improvement | — | 2025-12-16 | 2026-03-06 | 80 | $60K |
| BP2025-18995 | Improvement | — | 2025-09-26 | 2026-02-26 | 153 | $35K |