How long does a Demolition permit take in Taradale, Calgary?
Median days · Applied → Issued
10 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
18 days
From permit issuance to completion
City-wide median
4 days
Taradale is 6 days slower
Recent examples in Taradale
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-00896 | Demolition | Titan Contracting and Demolition | 2026-01-20 | 2026-01-23 | 3 | $0 |
| BP2025-23485 | Demolition | Titan Contracting and Demolition | 2025-12-10 | 2025-12-11 | 1 | $0 |
| BP2025-20551 | Demolition | Gill S Express | 2025-10-21 | 2025-11-10 | 20 | $0 |
| BP2025-13765 | Demolition | First General Services | 2025-07-16 | 2025-08-01 | 16 | $0 |