How long does a Demolition permit take in Taradale, Calgary?

Rolling 24 months · Sample: 4
Median days · Applied → Issued
10 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
18 days
From permit issuance to completion
City-wide median
4 days
Taradale is 6 days slower

Recent examples in Taradale

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-00896DemolitionTitan Contracting and Demolition2026-01-202026-01-233$0
BP2025-23485DemolitionTitan Contracting and Demolition2025-12-102025-12-111$0
BP2025-20551DemolitionGill S Express2025-10-212025-11-1020$0
BP2025-13765DemolitionFirst General Services2025-07-162025-08-0116$0