How long does a Commercial / Multi Family Project permit take in Taradale, Calgary?

Rolling 24 months · Sample: 9
Median days · Applied → Issued
45 days
Sample: 9 permits, last 24 months
Median days · Issued → Completed
123 days
From permit issuance to completion
City-wide median
42 days
Taradale is 3 days slower

Recent examples in Taradale

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10049NewKamex Construction2026-06-032026-08-0563$75K
BP2026-10535Improvement2026-06-102026-07-2343$30K
BP2026-03605Improvement2026-03-092026-05-1567$200K
BP2024-25849Improvement2024-12-152025-12-12362$34K
BP2025-16935ImprovementPersimmon Contracting2025-08-292025-10-0840$150K