How long does a Commercial / Multi Family Project permit take in Taradale, Calgary?
Median days · Applied → Issued
45 days
Sample: 9 permits, last 24 months
Median days · Issued → Completed
123 days
From permit issuance to completion
City-wide median
42 days
Taradale is 3 days slower
Recent examples in Taradale
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10049 | New | Kamex Construction | 2026-06-03 | 2026-08-05 | 63 | $75K |
| BP2026-10535 | Improvement | — | 2026-06-10 | 2026-07-23 | 43 | $30K |
| BP2026-03605 | Improvement | — | 2026-03-09 | 2026-05-15 | 67 | $200K |
| BP2024-25849 | Improvement | — | 2024-12-15 | 2025-12-12 | 362 | $34K |
| BP2025-16935 | Improvement | Persimmon Contracting | 2025-08-29 | 2025-10-08 | 40 | $150K |