How long does a Demolition permit take in Springbank Hill, Calgary?
Median days · Applied → Issued
28 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
90 days
From permit issuance to completion
City-wide median
4 days
Springbank Hill is 24 days slower
Recent examples in Springbank Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05599 | Demolition | Creative Solutions Contracting Services | 2026-04-09 | 2026-05-08 | 29 | $0 |
| BP2026-05600 | Demolition | Creative Solutions Contracting Services | 2026-04-09 | 2026-05-06 | 27 | $0 |
| BP2026-05584 | Demolition | Creative Solutions Contracting Services | 2026-04-09 | 2026-04-20 | 11 | $0 |
| BP2025-19588 | Demolition | North Coast Excavation and Trucking | 2025-10-06 | 2025-11-03 | 28 | $0 |