How long does a Commercial / Multi Family Project permit take in Springbank Hill, Calgary?

Rolling 24 months · Sample: 46
Median days · Applied → Issued
64 days
Sample: 46 permits, last 24 months
Median days · Issued → Completed
251 days
From permit issuance to completion
City-wide median
42 days
Springbank Hill is 22 days slower

Recent examples in Springbank Hill

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-02312Improvement2026-02-162026-09-09205$500K
BP2026-14740NewTaylor2026-08-052026-08-2015$764K
BP2026-15244UnspecifiedSprouse Fire and Safety2026-08-122026-08-186$4K
BP2026-03651New2026-03-102026-08-04147$1M
BP2026-02014NewVesta Properties Aspen2026-02-102026-07-24164$32.1M