How long does a Residential Improvement Project permit take in Southwood, Calgary?
Median days · Applied → Issued
20 days
Sample: 90 permits, last 24 months
Median days · Issued → Completed
109 days
From permit issuance to completion
City-wide median
17 days
Southwood is 3 days slower
Recent examples in Southwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16473 | New | — | 2026-08-28 | 2026-09-10 | 13 | $91K |
| BP2026-14984 | New | — | 2026-08-08 | 2026-08-25 | 17 | $47K |
| BP2026-13943 | Improvement | — | 2026-07-24 | 2026-08-18 | 25 | $500 |
| BP2026-11930 | Improvement | Maxgreen Windows Siding and Roofing | 2026-06-27 | 2026-07-28 | 31 | $2K |
| BP2026-07577 | Improvement | Diamond Home Solutions | 2026-05-05 | 2026-07-23 | 79 | $0 |