How long does a Commercial / Multi Family Project permit take in Southwood, Calgary?
Median days · Applied → Issued
34 days
Sample: 46 permits, last 24 months
Median days · Issued → Completed
111 days
From permit issuance to completion
City-wide median
42 days
Southwood is 8 days faster
Recent examples in Southwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14186 | Improvement | Opus Corporation | 2026-07-28 | 2026-08-20 | 23 | $5K |
| BP2026-13723 | Improvement | — | 2026-07-22 | 2026-08-17 | 26 | $50K |
| BP2026-13405 | Improvement | Wii Projects | 2026-07-17 | 2026-08-13 | 27 | $365K |
| BP2026-05716 | Improvement | Graham Construction and Engineering | 2026-04-10 | 2026-08-12 | 124 | $28.3M |
| BP2026-06208 | New | Allure Luxury Homes | 2026-04-17 | 2026-08-11 | 116 | $1M |