How long does a Single Construction Permit permit take in Silverado, Calgary?

Rolling 24 months · Sample: 223
Median days · Applied → Issued
18 days
Sample: 223 permits, last 24 months
Median days · Issued → Completed
174 days
From permit issuance to completion
City-wide median
18 days
Same as Silverado

Recent examples in Silverado

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14798NewCardel Homes2026-08-062026-09-0429$263K
BP2026-09453NewExcel Homes2026-05-282026-08-2589$0
BP2026-15193NewCardel Homes2026-08-112026-08-2514$178K
BP2026-15195NewCardel Homes2026-08-112026-08-2514$158K
BP2026-11658NewCardel Homes2026-06-242026-08-1249$263K