How long does a Commercial / Multi Family Project permit take in Silverado, Calgary?
Median days · Applied → Issued
56 days
Sample: 33 permits, last 24 months
Median days · Issued → Completed
82 days
From permit issuance to completion
City-wide median
42 days
Silverado is 14 days slower
Recent examples in Silverado
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10696 | New | Mountain Pacific Homes | 2026-06-11 | 2026-08-04 | 54 | $2.2M |
| BP2026-02945 | New | Cardel Homes | 2026-02-26 | 2026-07-14 | 138 | $791K |
| BP2026-10695 | New | Mountain Pacific Homes | 2026-06-11 | 2026-06-30 | 19 | $2.5M |
| BP2026-10697 | New | Mountain Pacific Homes | 2026-06-11 | 2026-06-30 | 19 | $1.9M |
| BP2026-06465 | Improvement | — | 2026-04-21 | 2026-06-03 | 43 | $100K |