How long does a Single Construction Permit permit take in Shawnee Slopes, Calgary?

Rolling 24 months · Sample: 57
Median days · Applied → Issued
18 days
Sample: 57 permits, last 24 months
Median days · Issued → Completed
153 days
From permit issuance to completion
City-wide median
18 days
Same as Shawnee Slopes

Recent examples in Shawnee Slopes

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11065NewCardel Homes2026-06-162026-07-0822$356K
BP2026-09573NewCardel Homes2026-05-292026-06-1618$361K
BP2026-04676NewCardel Homes2026-03-252026-06-1279$470K
BP2026-03773NewCardel Homes2026-03-112026-05-0656$470K
BP2026-06408NewCardel Homes2026-04-202026-05-0212$482K