How long does a Single Construction Permit permit take in Shawnee Slopes, Calgary?
Median days · Applied → Issued
18 days
Sample: 57 permits, last 24 months
Median days · Issued → Completed
153 days
From permit issuance to completion
City-wide median
18 days
Same as Shawnee Slopes
Recent examples in Shawnee Slopes
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11065 | New | Cardel Homes | 2026-06-16 | 2026-07-08 | 22 | $356K |
| BP2026-09573 | New | Cardel Homes | 2026-05-29 | 2026-06-16 | 18 | $361K |
| BP2026-04676 | New | Cardel Homes | 2026-03-25 | 2026-06-12 | 79 | $470K |
| BP2026-03773 | New | Cardel Homes | 2026-03-11 | 2026-05-06 | 56 | $470K |
| BP2026-06408 | New | Cardel Homes | 2026-04-20 | 2026-05-02 | 12 | $482K |