How long does a Commercial / Multi Family Project permit take in Shawnee Slopes, Calgary?
Median days · Applied → Issued
79 days
Sample: 28 permits, last 24 months
Median days · Issued → Completed
164 days
From permit issuance to completion
City-wide median
42 days
Shawnee Slopes is 37 days slower
Recent examples in Shawnee Slopes
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06487 | Improvement | — | 2026-04-21 | 2026-05-27 | 36 | $50K |
| BP2026-03781 | Improvement | — | 2026-03-11 | 2026-05-20 | 70 | $10K |
| BP2025-11973 | Improvement | — | 2025-06-20 | 2025-07-25 | 35 | $100K |
| BP2025-03910 | Improvement | — | 2025-03-07 | 2025-05-29 | 83 | $100K |
| BP2025-02807 | New | Eagle Crest Construction | 2025-02-18 | 2025-05-15 | 86 | $1.7M |