How long does a Commercial / Multi Family Project permit take in Shawnee Slopes, Calgary?

Rolling 24 months · Sample: 28
Median days · Applied → Issued
79 days
Sample: 28 permits, last 24 months
Median days · Issued → Completed
164 days
From permit issuance to completion
City-wide median
42 days
Shawnee Slopes is 37 days slower

Recent examples in Shawnee Slopes

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-06487Improvement2026-04-212026-05-2736$50K
BP2026-03781Improvement2026-03-112026-05-2070$10K
BP2025-11973Improvement2025-06-202025-07-2535$100K
BP2025-03910Improvement2025-03-072025-05-2983$100K
BP2025-02807NewEagle Crest Construction2025-02-182025-05-1586$1.7M