How long does a Single Construction Permit permit take in Shaganappi, Calgary?
Median days · Applied → Issued
61 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
414 days
From permit issuance to completion
City-wide median
18 days
Shaganappi is 43 days slower
Recent examples in Shaganappi
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-07494 | New | Cornerstone by Dallaire Homes | 2026-05-04 | 2026-07-22 | 79 | $357K |
| BP2024-12328 | New | Sunset Homes | 2024-06-20 | 2025-07-22 | 397 | $316K |
| BP2024-12329 | New | Sunset Homes | 2024-06-20 | 2025-07-22 | 397 | $316K |
| BP2024-25808 | New | 2690508 Alberta | 2024-12-13 | 2025-06-10 | 179 | $221K |
| BP2024-25809 | New | 2690508 Alberta | 2024-12-13 | 2025-06-10 | 179 | $221K |