How long does a Single Construction Permit permit take in Shaganappi, Calgary?

Rolling 24 months · Sample: 17
Median days · Applied → Issued
61 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
414 days
From permit issuance to completion
City-wide median
18 days
Shaganappi is 43 days slower

Recent examples in Shaganappi

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07494NewCornerstone by Dallaire Homes2026-05-042026-07-2279$357K
BP2024-12328NewSunset Homes2024-06-202025-07-22397$316K
BP2024-12329NewSunset Homes2024-06-202025-07-22397$316K
BP2024-25808New2690508 Alberta2024-12-132025-06-10179$221K
BP2024-25809New2690508 Alberta2024-12-132025-06-10179$221K