How long does a Commercial / Multi Family Project permit take in Shaganappi, Calgary?
Median days · Applied → Issued
79 days
Sample: 39 permits, last 24 months
Median days · Issued → Completed
306 days
From permit issuance to completion
City-wide median
42 days
Shaganappi is 37 days slower
Recent examples in Shaganappi
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05989 | New | Winter Green Homes | 2026-04-15 | 2026-09-08 | 146 | $901K |
| BP2025-23082 | New | Altamura Homes | 2025-12-02 | 2026-06-24 | 204 | $596K |
| BP2026-04946 | New | Sunstar Homes | 2026-03-30 | 2026-06-17 | 79 | $1.2M |
| BP2026-07320 | Improvement | Fire Ant Contracting | 2026-05-01 | 2026-05-29 | 28 | $261K |
| BP2025-23081 | New | Altamura Homes | 2025-12-02 | 2026-05-28 | 177 | $772K |