How long does a Commercial / Multi Family Project permit take in Shaganappi, Calgary?

Rolling 24 months · Sample: 39
Median days · Applied → Issued
79 days
Sample: 39 permits, last 24 months
Median days · Issued → Completed
306 days
From permit issuance to completion
City-wide median
42 days
Shaganappi is 37 days slower

Recent examples in Shaganappi

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-05989NewWinter Green Homes2026-04-152026-09-08146$901K
BP2025-23082NewAltamura Homes2025-12-022026-06-24204$596K
BP2026-04946NewSunstar Homes2026-03-302026-06-1779$1.2M
BP2026-07320ImprovementFire Ant Contracting2026-05-012026-05-2928$261K
BP2025-23081NewAltamura Homes2025-12-022026-05-28177$772K