How long does a Residential Improvement Project permit take in Scenic Acres, Calgary?

Rolling 24 months · Sample: 87
Median days · Applied → Issued
17 days
Sample: 87 permits, last 24 months
Median days · Issued → Completed
78 days
From permit issuance to completion
City-wide median
17 days
Same as Scenic Acres

Recent examples in Scenic Acres

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15325ImprovementNational Fence and Deck2026-08-132026-09-0119$5K
BP2026-14177Improvement2026-07-282026-08-2730$25K
BP2026-09712ImprovementVarsity Contracting and Renovations2026-06-012026-08-1575$4K
BP2026-12250Improvement2026-07-022026-08-1241$100K
BP2026-12775ImprovementTrue North Concrete Cutting and Coring2026-07-092026-08-1234$4K

Other permit types in Scenic Acres