How long does a Commercial / Multi Family Project permit take in Scenic Acres, Calgary?
Median days · Applied → Issued
35 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
112 days
From permit issuance to completion
City-wide median
42 days
Scenic Acres is 7 days faster
Recent examples in Scenic Acres
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14730 | Improvement | Hbc Builders | 2026-08-05 | 2026-08-19 | 14 | $75K |
| BP2025-20275 | New | Kamex Construction | 2025-10-16 | 2025-12-02 | 47 | $270K |
| BP2025-20960 | Improvement | Crestview Electric | 2025-10-27 | 2025-11-15 | 19 | $113K |
| BP2025-13705 | Improvement | Delphi Electric | 2025-07-15 | 2025-08-19 | 35 | $150K |
| BP2024-20273 | Improvement | Graham Infrastructure | 2024-09-24 | 2024-12-18 | 85 | $1.5M |