How long does a Commercial / Multi Family Project permit take in Scenic Acres, Calgary?

Rolling 24 months · Sample: 7
Median days · Applied → Issued
35 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
112 days
From permit issuance to completion
City-wide median
42 days
Scenic Acres is 7 days faster

Recent examples in Scenic Acres

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14730ImprovementHbc Builders2026-08-052026-08-1914$75K
BP2025-20275NewKamex Construction2025-10-162025-12-0247$270K
BP2025-20960ImprovementCrestview Electric2025-10-272025-11-1519$113K
BP2025-13705ImprovementDelphi Electric2025-07-152025-08-1935$150K
BP2024-20273ImprovementGraham Infrastructure2024-09-242024-12-1885$1.5M