How long does a Single Construction Permit permit take in Scarboro, Calgary?
Median days · Applied → Issued
44 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
257 days
From permit issuance to completion
City-wide median
18 days
Scarboro is 26 days slower
Recent examples in Scarboro
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13204 | New | Lt Custom Homes | 2026-07-15 | 2026-08-11 | 27 | $575K |
| BP2025-02397 | New | William Blake Homes | 2025-02-10 | 2025-08-21 | 192 | $727K |
| BP2025-12703 | New | Cnj Developments | 2025-07-01 | 2025-07-24 | 23 | $637K |
| BP2024-22310 | New | Lt Custom Homes | 2024-10-20 | 2024-12-19 | 60 | $525K |