How long does a Residential Improvement Project permit take in Scarboro, Calgary?
Median days · Applied → Issued
15 days
Sample: 19 permits, last 24 months
Median days · Issued → Completed
218 days
From permit issuance to completion
City-wide median
17 days
Scarboro is 2 days faster
Recent examples in Scarboro
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13205 | New | Lt Custom Homes | 2026-07-15 | 2026-08-11 | 27 | $56K |
| BP2026-10348 | New | Strong Residential Projects | 2026-06-08 | 2026-07-10 | 32 | $65K |
| BP2026-06399 | Improvement | Birchstone Homes | 2026-04-20 | 2026-05-25 | 35 | $200K |
| BP2026-04082 | New | Solid Builds Construction | 2026-03-17 | 2026-05-11 | 55 | $83K |
| BP2026-06589 | Improvement | — | 2026-04-22 | 2026-04-28 | 6 | $66K |