How long does a Residential Improvement Project permit take in Scarboro/Sunalta West, Calgary?
Median days · Applied → Issued
20 days
Sample: 9 permits, last 24 months
Median days · Issued → Completed
124 days
From permit issuance to completion
City-wide median
17 days
Scarboro/Sunalta West is 3 days slower
Recent examples in Scarboro/Sunalta West
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14398 | Improvement | National Fence and Deck | 2026-07-30 | 2026-08-19 | 20 | $11K |
| BP2026-05699 | Improvement | Simply Stone Landscapes | 2026-04-10 | 2026-04-24 | 14 | $157K |
| BP2025-17311 | Improvement | — | 2025-09-04 | 2026-03-12 | 189 | $31K |
| BP2025-17782 | Improvement | — | 2025-09-11 | 2025-10-21 | 40 | $15K |
| BP2025-20225 | Improvement | Hearth and Home Fireplace Specialties | 2025-10-15 | 2025-10-17 | 2 | $2K |