How long does a Demolition permit take in Scarboro/Sunalta West, Calgary?
Median days · Applied → Issued
12 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
98 days
From permit issuance to completion
City-wide median
4 days
Scarboro/Sunalta West is 8 days slower
Recent examples in Scarboro/Sunalta West
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08214 | Demolition | Ovis Group | 2026-05-12 | 2026-05-15 | 3 | $0 |
| BP2026-05037 | Demolition | Blackwater Constructors | 2026-03-31 | 2026-05-13 | 43 | $0 |
| BP2026-05036 | Demolition | Blackwater Constructors | 2026-03-31 | 2026-04-20 | 20 | $0 |
| BP2026-05297 | Demolition | Kingsway Builders | 2026-04-06 | 2026-04-09 | 3 | $0 |