How long does a Demolition permit take in Scarboro/Sunalta West, Calgary?

Rolling 24 months · Sample: 4
Median days · Applied → Issued
12 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
98 days
From permit issuance to completion
City-wide median
4 days
Scarboro/Sunalta West is 8 days slower

Recent examples in Scarboro/Sunalta West

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08214DemolitionOvis Group2026-05-122026-05-153$0
BP2026-05037DemolitionBlackwater Constructors2026-03-312026-05-1343$0
BP2026-05036DemolitionBlackwater Constructors2026-03-312026-04-2020$0
BP2026-05297DemolitionKingsway Builders2026-04-062026-04-093$0