How long does a Single Construction Permit permit take in Sage Hill, Calgary?
Median days · Applied → Issued
52 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
290 days
From permit issuance to completion
City-wide median
18 days
Sage Hill is 34 days slower
Recent examples in Sage Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2024-24502 | New | Calbridge Homes | 2024-11-21 | 2024-11-26 | 5 | $350K |
| BP2024-19198 | New | Lupi Luxury Homes | 2024-09-10 | 2024-11-04 | 55 | $208K |
| BP2024-19199 | New | Lupi Luxury Homes | 2024-09-10 | 2024-11-04 | 55 | $207K |
| BP2024-18360 | New | Lupi Luxury Homes | 2024-08-30 | 2024-10-21 | 52 | $208K |
| BP2024-18361 | New | Lupi Luxury Homes | 2024-08-30 | 2024-10-21 | 52 | $210K |