How long does a Single Construction Permit permit take in Sage Hill, Calgary?

Rolling 24 months · Sample: 8
Median days · Applied → Issued
52 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
290 days
From permit issuance to completion
City-wide median
18 days
Sage Hill is 34 days slower

Recent examples in Sage Hill

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2024-24502NewCalbridge Homes2024-11-212024-11-265$350K
BP2024-19198NewLupi Luxury Homes2024-09-102024-11-0455$208K
BP2024-19199NewLupi Luxury Homes2024-09-102024-11-0455$207K
BP2024-18360NewLupi Luxury Homes2024-08-302024-10-2152$208K
BP2024-18361NewLupi Luxury Homes2024-08-302024-10-2152$210K