How long does a Commercial / Multi Family Project permit take in Sage Hill, Calgary?

Rolling 24 months · Sample: 107
Median days · Applied → Issued
57 days
Sample: 107 permits, last 24 months
Median days · Issued → Completed
229 days
From permit issuance to completion
City-wide median
42 days
Sage Hill is 15 days slower

Recent examples in Sage Hill

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12033ImprovementBuildwise Design and Construction2026-06-292026-09-0871$52K
BP2026-13517Improvement2026-07-202026-09-0446$585K
BP2026-13448Improvement2026-07-182026-09-0347$30K
BP2026-10992Improvement2026-06-162026-08-0550$110K
BP2026-11563NewTrico Homes2026-06-232026-07-3138$696K