How long does a Commercial / Multi Family Project permit take in Sage Hill, Calgary?
Median days · Applied → Issued
57 days
Sample: 107 permits, last 24 months
Median days · Issued → Completed
229 days
From permit issuance to completion
City-wide median
42 days
Sage Hill is 15 days slower
Recent examples in Sage Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12033 | Improvement | Buildwise Design and Construction | 2026-06-29 | 2026-09-08 | 71 | $52K |
| BP2026-13517 | Improvement | — | 2026-07-20 | 2026-09-04 | 46 | $585K |
| BP2026-13448 | Improvement | — | 2026-07-18 | 2026-09-03 | 47 | $30K |
| BP2026-10992 | Improvement | — | 2026-06-16 | 2026-08-05 | 50 | $110K |
| BP2026-11563 | New | Trico Homes | 2026-06-23 | 2026-07-31 | 38 | $696K |