How long does a Single Construction Permit permit take in Roxboro, Calgary?

Rolling 24 months · Sample: 3
Median days · Applied → Issued
90 days
Sample: 3 permits, last 24 months
City-wide median
18 days
Roxboro is 72 days slower

Recent examples in Roxboro

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15740New2026-08-192026-09-0820$0
BP2026-01640NewDream Ridge Homes2026-02-032026-05-0490$672K
BP2024-22545NewMaillot Homes2024-10-232025-01-2998$561K