How long does a Residential Improvement Project permit take in Roxboro, Calgary?
Median days · Applied → Issued
22 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
274 days
From permit issuance to completion
City-wide median
17 days
Roxboro is 5 days slower
Recent examples in Roxboro
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15625 | Improvement | Planta Landscape | 2026-08-17 | 2026-09-08 | 22 | $7K |
| BP2026-01642 | New | Dream Ridge Homes | 2026-02-03 | 2026-05-04 | 90 | $75K |
| BP2025-08263 | Improvement | Armstrong Home Renos | 2025-05-05 | 2025-05-27 | 22 | $25K |
| BP2025-03179 | Improvement | Hearth and Home Fireplace Specialties | 2025-02-25 | 2025-03-03 | 6 | $2K |
| BP2024-22546 | New | Maillot Homes | 2024-10-23 | 2025-01-29 | 98 | $47K |