How long does a Residential Improvement Project permit take in Rosscarrock, Calgary?

Rolling 24 months · Sample: 46
Median days · Applied → Issued
34 days
Sample: 46 permits, last 24 months
Median days · Issued → Completed
140 days
From permit issuance to completion
City-wide median
17 days
Rosscarrock is 17 days slower

Recent examples in Rosscarrock

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12819Improvement2026-07-092026-08-1941$20K
BP2026-11111NewSkylark Custom Homes2026-06-172026-07-3144$39K
BP2026-11113NewSkylark Custom Homes2026-06-172026-07-3144$39K
BP2026-03116Improvement2026-03-022026-05-0463$2K
BP2026-00921ImprovementAwelo Plumbing and Heating2026-01-202026-04-0878$75K