How long does a Commercial / Multi Family Project permit take in Rosscarrock, Calgary?
Median days · Applied → Issued
80 days
Sample: 32 permits, last 24 months
Median days · Issued → Completed
283 days
From permit issuance to completion
City-wide median
42 days
Rosscarrock is 38 days slower
Recent examples in Rosscarrock
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-23827 | New | High Rock Developments | 2025-12-17 | 2026-07-28 | 223 | $1.3M |
| BP2026-03334 | New | Samdisha Homes | 2026-03-04 | 2026-07-23 | 141 | $758K |
| BP2026-03335 | New | Samdisha Homes | 2026-03-04 | 2026-07-09 | 127 | $758K |
| BP2026-10508 | Improvement | — | 2026-06-09 | 2026-06-16 | 7 | $80K |
| BP2026-00966 | New | Livespace Designer Homes | 2026-01-21 | 2026-06-15 | 145 | $752K |