How long does a Commercial / Multi Family Project permit take in Rosscarrock, Calgary?

Rolling 24 months · Sample: 32
Median days · Applied → Issued
80 days
Sample: 32 permits, last 24 months
Median days · Issued → Completed
283 days
From permit issuance to completion
City-wide median
42 days
Rosscarrock is 38 days slower

Recent examples in Rosscarrock

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2025-23827NewHigh Rock Developments2025-12-172026-07-28223$1.3M
BP2026-03334NewSamdisha Homes2026-03-042026-07-23141$758K
BP2026-03335NewSamdisha Homes2026-03-042026-07-09127$758K
BP2026-10508Improvement2026-06-092026-06-167$80K
BP2026-00966NewLivespace Designer Homes2026-01-212026-06-15145$752K