How long does a Residential Improvement Project permit take in Redstone, Calgary?
Median days · Applied → Issued
27 days
Sample: 188 permits, last 24 months
Median days · Issued → Completed
89 days
From permit issuance to completion
City-wide median
17 days
Redstone is 10 days slower
Recent examples in Redstone
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15894 | New | — | 2026-08-20 | 2026-09-09 | 20 | $51K |
| BP2026-14561 | New | Titan Pro Developer | 2026-08-03 | 2026-09-03 | 31 | $51K |
| BP2026-14010 | New | — | 2026-07-26 | 2026-08-19 | 24 | $47K |
| BP2026-10874 | New | — | 2026-06-15 | 2026-08-17 | 63 | $59K |
| BP2026-11392 | Improvement | — | 2026-06-21 | 2026-08-17 | 57 | $0 |