How long does a Commercial / Multi Family Project permit take in Redstone, Calgary?
Median days · Applied → Issued
46 days
Sample: 59 permits, last 24 months
Median days · Issued → Completed
350 days
From permit issuance to completion
City-wide median
42 days
Redstone is 4 days slower
Recent examples in Redstone
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10989 | New | Wilco Contractors Southwest | 2026-06-16 | 2026-09-07 | 83 | $725K |
| BP2026-15232 | New | Streetside Development | 2026-08-12 | 2026-08-28 | 16 | $1.6M |
| BP2026-09148 | New | Streetside Development | 2026-05-25 | 2026-08-14 | 81 | $1.1M |
| BP2026-11687 | Improvement | Sanjh Construction | 2026-06-24 | 2026-07-30 | 36 | $150K |
| BP2026-06726 | Improvement | — | 2026-04-24 | 2026-06-11 | 48 | $1.2M |