How long does a Commercial / Multi Family Project permit take in Redstone, Calgary?

Rolling 24 months · Sample: 59
Median days · Applied → Issued
46 days
Sample: 59 permits, last 24 months
Median days · Issued → Completed
350 days
From permit issuance to completion
City-wide median
42 days
Redstone is 4 days slower

Recent examples in Redstone

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10989NewWilco Contractors Southwest2026-06-162026-09-0783$725K
BP2026-15232NewStreetside Development2026-08-122026-08-2816$1.6M
BP2026-09148NewStreetside Development2026-05-252026-08-1481$1.1M
BP2026-11687ImprovementSanjh Construction2026-06-242026-07-3036$150K
BP2026-06726Improvement2026-04-242026-06-1148$1.2M