How long does a Residential Improvement Project permit take in Pineridge, Calgary?
Median days · Applied → Issued
22 days
Sample: 72 permits, last 24 months
Median days · Issued → Completed
73 days
From permit issuance to completion
City-wide median
17 days
Pineridge is 5 days slower
Recent examples in Pineridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10364 | New | — | 2026-06-08 | 2026-09-08 | 92 | $140K |
| BP2026-15404 | Improvement | — | 2026-08-13 | 2026-08-27 | 14 | $23K |
| BP2026-14013 | New | Urban Crew Landscaping and Construction | 2026-07-26 | 2026-08-19 | 24 | $47K |
| BP2026-04487 | Improvement | Continent Constructions | 2026-03-23 | 2026-08-18 | 148 | $64K |
| BP2026-13057 | Improvement | — | 2026-07-13 | 2026-08-13 | 31 | $5K |