How long does a Residential Improvement Project permit take in Pineridge, Calgary?

Rolling 24 months · Sample: 72
Median days · Applied → Issued
22 days
Sample: 72 permits, last 24 months
Median days · Issued → Completed
73 days
From permit issuance to completion
City-wide median
17 days
Pineridge is 5 days slower

Recent examples in Pineridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10364New2026-06-082026-09-0892$140K
BP2026-15404Improvement2026-08-132026-08-2714$23K
BP2026-14013NewUrban Crew Landscaping and Construction2026-07-262026-08-1924$47K
BP2026-04487ImprovementContinent Constructions2026-03-232026-08-18148$64K
BP2026-13057Improvement2026-07-132026-08-1331$5K