How long does a Commercial / Multi Family Project permit take in Pineridge, Calgary?
Median days · Applied → Issued
45 days
Sample: 28 permits, last 24 months
Median days · Issued → Completed
98 days
From permit issuance to completion
City-wide median
42 days
Pineridge is 3 days slower
Recent examples in Pineridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11095 | Improvement | EllisDon Construction | 2026-06-17 | 2026-08-24 | 68 | $32.6M |
| BP2026-11298 | Improvement | Ziggurat Construction | 2026-06-19 | 2026-07-13 | 24 | $163K |
| BP2026-03552 | New | — | 2026-03-09 | 2026-07-03 | 116 | $1M |
| BP2026-07271 | Improvement | — | 2026-04-30 | 2026-05-25 | 25 | $523K |
| BP2025-24009 | Improvement | — | 2025-12-19 | 2026-04-14 | 116 | $82K |