How long does a Residential Improvement Project permit take in Parkland, Calgary?

Rolling 24 months · Sample: 74
Median days · Applied → Issued
22 days
Sample: 74 permits, last 24 months
Median days · Issued → Completed
103 days
From permit issuance to completion
City-wide median
17 days
Parkland is 5 days slower

Recent examples in Parkland

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14634ImprovementIn Construction2026-08-042026-09-0936$200K
BP2026-16368ImprovementDesignspace Kuchen2026-08-272026-09-0812$120K
BP2026-14050NewNational Fence and Deck2026-07-272026-08-2529$8K
BP2026-13317Improvement2026-07-162026-08-0520$25K
BP2026-04348New2026-03-202026-07-30132$56K