How long does a Residential Improvement Project permit take in Parkland, Calgary?
Median days · Applied → Issued
22 days
Sample: 74 permits, last 24 months
Median days · Issued → Completed
103 days
From permit issuance to completion
City-wide median
17 days
Parkland is 5 days slower
Recent examples in Parkland
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14634 | Improvement | In Construction | 2026-08-04 | 2026-09-09 | 36 | $200K |
| BP2026-16368 | Improvement | Designspace Kuchen | 2026-08-27 | 2026-09-08 | 12 | $120K |
| BP2026-14050 | New | National Fence and Deck | 2026-07-27 | 2026-08-25 | 29 | $8K |
| BP2026-13317 | Improvement | — | 2026-07-16 | 2026-08-05 | 20 | $25K |
| BP2026-04348 | New | — | 2026-03-20 | 2026-07-30 | 132 | $56K |