How long does a Commercial / Multi Family Project permit take in Parkland, Calgary?

Rolling 24 months · Sample: 3
Median days · Applied → Issued
55 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
316 days
From permit issuance to completion
City-wide median
42 days
Parkland is 13 days slower

Recent examples in Parkland

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2025-22442Improvement2025-11-202026-01-1455$5.6M
BP2024-17750New2024-08-232024-12-18117$69K
BP2024-21278ImprovementTayo Construction2024-10-072024-10-2316$464K