How long does a Single Construction Permit permit take in Parkdale, Calgary?
Median days · Applied → Issued
28 days
Sample: 30 permits, last 24 months
Median days · Issued → Completed
292 days
From permit issuance to completion
City-wide median
18 days
Parkdale is 10 days slower
Recent examples in Parkdale
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15388 | New | Singh Homes | 2026-08-13 | 2026-09-08 | 26 | $345K |
| BP2026-15392 | New | Singh Homes | 2026-08-13 | 2026-09-08 | 26 | $312K |
| BP2026-06339 | New | Bhinder Homes | 2026-04-20 | 2026-06-30 | 71 | $331K |
| BP2026-06341 | New | Bhinder Homes | 2026-04-20 | 2026-06-30 | 71 | $331K |
| BP2026-02839 | New | Ace Homes | 2026-02-25 | 2026-03-27 | 30 | $434K |