Rolling 24 months · Sample: 47
Median days · Applied → Issued
26 days
Sample: 47 permits, last 24 months
Median days · Issued → Completed
190 days
From permit issuance to completion
City-wide median
17 days
Parkdale is 9 days slower

Recent examples in Parkdale

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15389NewSingh Homes2026-08-132026-09-0826$38K
BP2026-15393NewSingh Homes2026-08-132026-09-0826$38K
BP2026-09639ImprovementJ Staples Carpentry2026-05-292026-08-1780$77K
BP2026-02748ImprovementVc Contracting2026-02-242026-07-14140$56K
BP2026-06340NewBhinder Homes2026-04-202026-06-3071$38K