How long does a Single Construction Permit permit take in Osprey Hill, Calgary?
Median days · Applied → Issued
23 days
Sample: 34 permits, last 24 months
Median days · Issued → Completed
183 days
From permit issuance to completion
City-wide median
18 days
Osprey Hill is 5 days slower
Recent examples in Osprey Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14590 | New | Bedrock Homes | 2026-08-04 | 2026-08-31 | 27 | $398K |
| BP2026-12105 | New | Bedrock Homes | 2026-06-30 | 2026-07-29 | 29 | $376K |
| BP2026-11571 | New | Homes by Avi | 2026-06-23 | 2026-07-19 | 26 | $408K |
| BP2026-10925 | New | Homes by Avi | 2026-06-15 | 2026-07-03 | 18 | $340K |
| BP2026-09713 | New | Bedrock Homes | 2026-06-01 | 2026-06-19 | 18 | $350K |