How long does a Commercial / Multi Family Project permit take in Osprey Hill, Calgary?
Median days · Applied → Issued
56 days
Sample: 11 permits, last 24 months
Median days · Issued → Completed
215 days
From permit issuance to completion
City-wide median
42 days
Osprey Hill is 14 days slower
Recent examples in Osprey Hill
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-04913 | New | Homes by Avi | 2026-03-30 | 2026-08-04 | 127 | $1.5M |
| BP2026-06647 | New | Homes by Avi | 2026-04-23 | 2026-07-27 | 95 | $1.8M |
| BP2026-05891 | New | Homes by Avi | 2026-04-14 | 2026-07-25 | 102 | $1.8M |
| BP2026-05085 | New | Homes by Avi | 2026-04-01 | 2026-07-06 | 96 | $1.8M |
| BP2026-08806 | New | Homes by Avi | 2026-05-20 | 2026-06-26 | 37 | $1.5M |