How long does a Demolition permit take in Ogden, Calgary?
Median days · Applied → Issued
4 days
Sample: 16 permits, last 24 months
Median days · Issued → Completed
99 days
From permit issuance to completion
City-wide median
4 days
Same as Ogden
Recent examples in Ogden
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15654 | Demolition | Mozy Construction | 2026-08-18 | 2026-08-20 | 2 | $0 |
| BP2026-14292 | Demolition | Ovis Group | 2026-07-29 | 2026-07-30 | 1 | $0 |
| BP2026-13003 | Demolition | Cloverhill Construction | 2026-07-13 | 2026-07-14 | 1 | $0 |
| BP2026-10015 | Demolition | Elevated House Moving | 2026-06-03 | 2026-06-04 | 1 | $0 |
| BP2026-09338 | Demolition | Rocky View Excavation | 2026-05-27 | 2026-06-02 | 6 | $0 |