How long does a Commercial / Multi Family Project permit take in Ogden, Calgary?

Rolling 24 months · Sample: 28
Median days · Applied → Issued
27 days
Sample: 28 permits, last 24 months
Median days · Issued → Completed
61 days
From permit issuance to completion
City-wide median
42 days
Ogden is 15 days faster

Recent examples in Ogden

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16316Unspecified2026-08-262026-08-271$4K
BP2026-12907NewGood Earth Builders2026-07-102026-08-2445$810K
BP2026-12256ImprovementRocky Cross Construction North Dba Dki Calgary2026-07-022026-07-2422$2K
BP2026-12350ImprovementConte Contracting2026-07-032026-07-2421$134K
BP2026-10454ImprovementGreenfox Windows and Doors2026-06-092026-07-0627$4K