How long does a Commercial / Multi Family Project permit take in Ogden, Calgary?
Median days · Applied → Issued
27 days
Sample: 28 permits, last 24 months
Median days · Issued → Completed
61 days
From permit issuance to completion
City-wide median
42 days
Ogden is 15 days faster
Recent examples in Ogden
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16316 | Unspecified | — | 2026-08-26 | 2026-08-27 | 1 | $4K |
| BP2026-12907 | New | Good Earth Builders | 2026-07-10 | 2026-08-24 | 45 | $810K |
| BP2026-12256 | Improvement | Rocky Cross Construction North Dba Dki Calgary | 2026-07-02 | 2026-07-24 | 22 | $2K |
| BP2026-12350 | Improvement | Conte Contracting | 2026-07-03 | 2026-07-24 | 21 | $134K |
| BP2026-10454 | Improvement | Greenfox Windows and Doors | 2026-06-09 | 2026-07-06 | 27 | $4K |