How long does a Residential Improvement Project permit take in Oakridge, Calgary?
Median days · Applied → Issued
16 days
Sample: 79 permits, last 24 months
Median days · Issued → Completed
175 days
From permit issuance to completion
City-wide median
17 days
Oakridge is 1 days faster
Recent examples in Oakridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13788 | Improvement | Lukacs Studios | 2026-07-22 | 2026-08-20 | 29 | $150K |
| BP2026-09816 | Improvement | — | 2026-06-01 | 2026-06-26 | 25 | $40K |
| BP2026-10945 | Improvement | — | 2026-06-15 | 2026-06-24 | 9 | $11K |
| BP2025-24196 | New | Gkn Holdings LTD | 2025-12-24 | 2026-06-18 | 176 | $0 |
| BP2026-07161 | Improvement | — | 2026-04-29 | 2026-06-18 | 50 | $13K |