How long does a Demolition permit take in Oakridge, Calgary?

Rolling 24 months · Sample: 3
Median days · Applied → Issued
7 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
160 days
From permit issuance to completion
City-wide median
4 days
Oakridge is 3 days slower

Recent examples in Oakridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-09012DemolitionProject Wize2026-05-222026-06-0110$0
BP2026-05188DemolitionCreative Solutions Contracting Services2026-04-022026-04-097$0
BP2025-12195DemolitionPriestly Demolition2025-06-242025-06-273$0