How long does a Residential Improvement Project permit take in North Glenmore Park, Calgary?
Median days · Applied → Issued
33 days
Sample: 81 permits, last 24 months
Median days · Issued → Completed
164 days
From permit issuance to completion
City-wide median
17 days
North Glenmore Park is 16 days slower
Recent examples in North Glenmore Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11168 | New | Aspect Builders | 2026-06-17 | 2026-08-07 | 51 | $134K |
| BP2026-12591 | New | — | 2026-07-07 | 2026-08-06 | 30 | $56K |
| BP2026-12489 | New | Ak Design and Development | 2026-07-06 | 2026-08-05 | 30 | $42K |
| BP2026-10446 | Improvement | — | 2026-06-09 | 2026-08-04 | 56 | $21K |
| BP2026-12079 | Improvement | Bln Contracting | 2026-06-29 | 2026-08-04 | 36 | $44K |