How long does a Demolition permit take in North Glenmore Park, Calgary?
Median days · Applied → Issued
2 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
45 days
From permit issuance to completion
City-wide median
4 days
North Glenmore Park is 2 days faster
Recent examples in North Glenmore Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12570 | Demolition | Moxons Furniture Services | 2026-07-07 | 2026-07-09 | 2 | $0 |
| BP2026-11237 | Demolition | Western One Excavation | 2026-06-18 | 2026-06-22 | 4 | $0 |
| BP2026-11268 | Demolition | Western One Excavation | 2026-06-18 | 2026-06-22 | 4 | $0 |
| BP2026-11042 | Demolition | Ark Construction | 2026-06-16 | 2026-06-17 | 1 | $0 |
| BP2026-09848 | Demolition | Cloverhill Construction | 2026-06-01 | 2026-06-02 | 1 | $0 |